How long do renovation works take in Geneva?

Planning building work? Apartment, house or building renovation, a new storey or a roof extension, running the project is our job.

There is no standard duration for a renovation in Geneva. It depends on the permit procedure, the scale of the works, the condition of the building and the availability of contractors. HMG Construction Management SA draws up a dated schedule for each project after the site visit, then keeps it up to date until acceptance.

By Haïtam Mennana, HMG Construction Management SA, registered MPQ agent

What does the length of a renovation depend on?

The length of a project is not just the time tradespeople spend on site. It starts with the first studies and ends with acceptance and the final account. In between, several factors weigh more heavily than the floor area being renovated.

  • The permit procedure, if one is needed, and the quality of the file submitted.
  • The actual condition of the building, known only after a survey and, in an older building, an asbestos, PCB and lead inspection.
  • The number of trades involved and how they follow one another.
  • Lead times for certain materials and equipment, which need ordering early.
  • Whether the building is occupied during the works, which often means working in stages.
  • How quickly the owner takes decisions on finishes and options.

That is why an honest estimate can only be given after a visit. A figure quoted before anyone has seen the building mostly leads to disappointment.

Does the permit stage count?

Yes, whenever the works need one. In Geneva, permits are issued by the Office des autorisations de construire (OAC), the cantonal permit office. The official page Types d'autorisations (in French) distinguishes the fast-track procedure, known as APA, intended among other things for interior alterations and works that do not change the general appearance of the building, from the full application, known as DD, which covers everything else. Complete demolition requires a separate application.

The time the review takes varies with the procedure and with what the project involves. A complete file from the outset, prepared on the AC-Démat platform (in French), limits requests for further information, a frequent cause of waiting. If the project raises questions about siting, height or volume, a preliminary application, known as DP, can help before detailed drawings are produced.

What happens before the contractors arrive?

  1. Site visit, survey of the building and definition of the works you want.
  2. Hazardous materials survey in an older building, as described on the Canton's page Rénover, transformer ou démolir sans danger (in French).
  3. Plans, cost estimate and choice of permit procedure.
  4. Permit application and, for energy works, a grant application to the Programme Bâtiments (in French) before the works begin.
  5. Tendering, comparison of bids and signing of contracts.
  6. Ordering of long lead-time materials and site preparation.

These stages often take longer than clients expect, but they are what make an uninterrupted site possible. Several of them can run in parallel if the schedule is well put together.

Why do building works fall behind?

Delays rarely have a single cause. The most common are discoveries in the existing building, a decision that is slow to come, a change requested along the way or a contractor who does not follow on in time. One late delivery can hold up several trades at once.

The calendar matters too. The summer and year-end holidays, when many contractors close, need to be planned for from the start. In an occupied flat or a hotel that stays open, the hours available for noisy work are limited, which lengthens the works but keeps the building in use.

How does HMG keep a renovation on schedule?

HMG draws up a master schedule from the first studies, then detailed schedules for the construction phase. The firm identifies the tasks that drive the completion date, those where a lost day affects the whole project, and watches them closely.

During the works, site meetings are used to check each contractor's progress, anticipate deliveries and secure the decisions that are yours to take in good time. When something unexpected happens, HMG sets out its effect on the schedule and the cost, with the available options, before any decision is made.

Our guide on avoiding budget and schedule overruns covers these methods in more detail, and our page on works scheduling in Geneva describes the service.

Who should you call first for a realistic schedule?

You can hand the whole project to HMG, which then draws up a single schedule from the plans to acceptance, permit included. If you already have an architect for the design and the permit, HMG takes over the file once the permit is granted, working with the architect, and builds the construction schedule from their drawings.

Renovations managed by HMG

Frequently asked questions about renovation timescales in Geneva

Can I know how long it will take before there are any plans?

Only in very broad terms. A reliable timescale needs a visit, a survey and a first definition of the works. HMG gives you a dated schedule after that stage and refines it with each decision.

Is an APA always quicker than a DD?

APA is the fast-track procedure, intended for simpler works. The actual time still depends on the quality of the file and on any further information requested. The Canton's page Types d'autorisations (in French) shows which procedure applies to your works.

Can I stay in my home during the works?

Often, yes, if the site is organised by zones. The works then take longer, but you keep the use of part of your home. Our page on apartment renovation in Geneva explains how this works.

Are deadlines written into the contractors' contracts?

They can be, and it is advisable. HMG writes each contractor's deadlines into its contract and into the master schedule, so that everyone's commitments can be tracked.

Can a hotel or a shop be renovated without closing?

Yes, with a phased schedule and adapted working hours. Our article on renovating a hotel without closing describes the approach.