How do you renovate a hotel or restaurant without closing?

Planning building work? Apartment, house or building renovation, a new storey or a roof extension, running the project is our job.

Renovating a hotel without closing relies on a schedule floor by floor or wing by wing, work zones kept apart from guests and close coordination with the operating team. HMG Construction Management SA has managed seven hotel renovations and uses this method so that the hotel keeps welcoming guests throughout the works.

By Haïtam Mennana, HMG Construction Management SA, registered MPQ agent

Can a hotel really be renovated without closing?

Yes, for most kinds of work. Rooms, corridors, facades and much of the public areas can be renovated in stages while the rest of the hotel carries on as normal. The hotel takes some of its rooms off sale, then gets them back once they are finished.

Some work does require a zone to close for a limited time, such as the main kitchen or a plant installation serving the whole building. What matters is to identify these at the start of the project, so they can be scheduled when they cause the least disruption.

How do you split up the works?

  • By floor or by wing. A whole floor closed off is easier to isolate than scattered rooms, and workers do not cross paths with guests.
  • In batches of rooms. When the hotel cannot close a floor, rooms are handled in groups, with temporary partitions and floor protection.
  • With a sample room. A first finished room lets you approve the finishes and measure the real working time before the series starts.
  • With a separate access. Workers and materials use a service entrance and a dedicated lift, well away from reception.
  • With agreed hours. Noisy work is concentrated at the times when fewest guests are present, as set by the hotel's management.

The schedule, a shared tool for the hotel and the site

In a working hotel, the works schedule and the booking plan have to be read together. Every room off sale costs the operator money, and every day of delay adds to that cost. The schedule therefore fixes the dates when each batch of rooms leaves and returns to sale, and the reservations team plans around it.

Materials with long delivery times are ordered early, so that no batch is held up waiting for a supply. The hotel's busiest periods are protected, with the heaviest phases placed outside them. Our page on works scheduling in Geneva explains how HMG builds these schedules.

What about a restaurant?

A restaurant has less room for manoeuvre, because the dining room and the kitchen often form a single space. The works are therefore prepared well in advance, to keep the time on site as short as possible. Part of the work can be done on the usual closing days or outside service hours, while another part requires a short closure planned ahead.

The kitchen remains the sensitive point, since the whole service depends on it. Equipment is ordered, checked and ready before it reaches the site, and the contractors follow a tight sequence so that the restaurant reopens on the announced date.

How HMG manages a hotel renovation while it stays open

HMG has managed seven hotel renovations, as well as restaurants and clinics, places where the site sits alongside guests or patients every day. The firm becomes the hotel management's single contact for everything to do with the works.

  • It calculates the cost, consults the contractors and compares their bids in light of the operating constraints.
  • It draws up the batch schedule with the operator, then keeps it up to date.
  • It chairs the site meetings, checks the work against SIA standards (the Swiss Society of Engineers and Architects) and tracks the costs.
  • It inspects each batch of rooms before it goes back on sale, with a list of defects to put right.

If the project has no plans yet, HMG draws them up and files the permit application as an agent registered on the Geneva MPQ list (mandataires professionnellement qualifiés, the cantonal register of qualified building professionals). If an architect designed the renovation, HMG takes over the file once the permit is granted, working with them.

Permits in Geneva for a hotel renovation

In Geneva, the permit comes from the Office des autorisations de construire (OAC), the cantonal permit office. Interior alterations and work that leaves the building's general appearance unchanged fall under the fast-track APA procedure, and everything else needs a full application (DD), according to the official page on permit types (in French). Applications are filed on the AC-Démat platform.

In an older building, a survey for asbestos, PCB and lead comes before the works, as the page Rénover, transformer ou démolir sans danger (in French) explains. It is best done early, since its results can change how the site is phased.

The stages of renovating a hotel that stays open

  1. Survey of the existing building and the operating constraints with the hotel's management.
  2. Works programme, cost estimate and choice of permit procedure.
  3. Batch schedule, aligned with the booking plan.
  4. Tendering, bid comparison and early ordering of long-lead supplies.
  5. Sample room, then renovation batch by batch.
  6. Acceptance of each batch and return of the rooms to sale.
  7. Final acceptance and final account.

Hotels and restaurants managed by HMG

Frequently asked questions on renovating a hotel without closing in Geneva

Does the hotel have to close to refurbish the rooms?

Usually not. Rooms are renovated floor by floor or in batches, taken off sale for the duration, while the rest of the hotel stays open.

How can disruption to guests be kept down?

By isolating the work zones, reserving an entrance and a lift for the workers, and grouping noisy work into hours agreed with the hotel's management.

Do you need a permit to renovate a hotel in Geneva?

It depends on the works. Interior alterations generally fall under the fast-track procedure, other work under a full application, according to the Canton's page on permit types (in French).

Can a restaurant be renovated without closing?

Part of the work can be done outside service hours or on closing days. Work on the kitchen often requires a short closure, which is prepared so as to keep it to a minimum.

When should preparation start?

As early as possible. The schedule has to fit around bookings and long-lead supplies must be ordered in advance, which takes time before the first day on site.